Armley Gyratory

Milestones

  • First consultation

    March 2018

     

    -

     

    April 2018

  • Second consultation

    Sept 2019

     

    -

     

    Oct 2019

  • Planning and funding approval

    Jan 22

     

    -

     

    Complete

  • Start construction

    Jan 2022

     

    -

     

    Dec 2022

    Off highways works and site clearance
  • First full closure weekend

    8 April

     

    -

     

    11 April

    Preparing traffic management, burning lines, introducing narrower lanes and 30mph speeds.
  • On highways construction (phase one)

    May 2022

     

    -

     

    Summer 2023

    Works to re-align and widen the highways to increase the capacity
  • On highways construction complete

    Dec 2022

     

    -

     

    Winter 2023/24

    Construction complete on highway works to provide the additional capacity that Armley Gyratory needs. Works on site will carry on subject to ground conditions until winter 2023/24.
  • Construction start on structures (phase two)

    Autumn 2023

     

    -

     

    Summer 2024

    Subject to obtaining relevant approvals
  • Construction scheme completed

    Winter 2024/25

     

    -

     

    End date